The Ferndale Reserve change rooms and amenities are getting an upgrade.
Located at the intersection of Blancoa and Metcalfe Roads, Ferndale Reserve currently features three full-sized senior ovals, a club room, change rooms and a Scout / Guide hall.
It is home to three active sporting clubs and supports multiple sporting codes throughout the year.
To meet the evolving needs of the community and ensure the facility remains inclusive, safe, and fit-for-purpose, the project will deliver new infrastructure. Key elements of the project include:
- Construction of new gender-neutral change rooms, ensuring safe and inclusive facilities for all users.
- Social hall with amenities, including new amenities to better support club functions and community events.
- New storage areas to accommodate growing participation and equipment needs.
- Accessibility provisions throughout the facility, ensuring compliance with current standards and equitable access for all.
- Improved viewing access to all three playing fields to enhance the spectator experience and support community engagement.
This investment will future proof the site, promote gender equity, and strengthen community participation in sport and recreation.
Tender opening soon
Keep your eyes out for the tendering opportunity to deliver the Ferndale Park Pavilion works. You will be able to apply for the tender in November 2025.
Project timeline
-
1/7/25 – Project started
The Ferndale Reserve project officially started the planning process on 1 July 2025.
-
24/11/25 – Planned tender award
The planning and tendering processes are anticipated to wrap-up by the end of November 2025.
-
2/3/26 – Planned construction commencement
The aim is to start the construction works in March 2026, depending on the successful awarding of the tender.
-
18/12/26 – Planned practical completion
The project's goal is to have practical completion of the works done by the end of 2026.
-
31/3/27 – Planned project completion
The goal is to have the new change rooms and amenities available for community use by the end of March 2027.